BCI Minerals has reached 69% construction progress at its Mardie Salt and Potash Project in Australia, with the first salt shipment expected by late 2026. The AUD 1.44B project is currently on budget with 77% of the pond area now inundated.
Offtake agreements already secure 62% of forecast output for the first three years, primarily targeting Asia-Pacific markets. The project also includes a sulphate of potash (SOP) by-product phase aiming to supply 30% of Australia’s domestic demand.